At U.S. 1 and SE Bridge Road, two different Florida Department of Transportation projects meet on the map. To the north, a 12-foot paved shared-use path is listed on FDOT's Treasure Coast construction page among active projects. To the south, the continuation toward the Nathaniel P. Reed Hobe Sound National Wildlife Refuge has its construction money in fiscal year 2029.
Over the next few years, that intersection becomes the edge of Hobe Sound's separated bike network. Anyone planning a ride, a run or a stroller loop around the farm stand, the refuge or Jonathan Dickinson State Park will plan around Bridge Road.
What FDOT Is Building North of Bridge Road
The active contract is T4738. It bundles two pieces of work under one schedule. The first is a resurfacing, restoration and rehabilitation job on U.S. 1. It runs 5.1 miles, from 0.5 mile south of the SR-A1A/SE Dixie Highway junction to Osprey Street. The second is a SUN Trail path along 3.07 miles of that same road, from Bridge Road to SE Osprey Street.
FDOT's project page describes the path as 12 feet wide and paved, built for bicyclists and pedestrians, and physically separated from vehicle traffic. It runs along the west side of U.S. 1. The contract was let on April 29, 2026, and FDOT set August 22, 2026 as the anticipated start. The project page lists an estimated construction cost of $15,994,700 and anticipated completion in Summer 2028. The contract now appears among the district's active Treasure Coast projects. FDOT held a construction open house for the project on August 6, 2026, at the Hobe Sound Civic Center, 8980 SE Olympus Street.
The roadway half of the contract goes well beyond fresh asphalt. FDOT's scope includes:
- Drainage improvements at the SE Bridge Road and Petty Street intersections, and at other spots along the corridor where water stands today
- Guardrail along the corridor upgraded to current standards
- Curb returns and ramps rebuilt to meet Americans with Disabilities Act standards
- New and upgraded signs and pavement markings with higher reflectivity
- A new sidewalk from Highbourne Way to the Jonathan Dickinson State Park entrance, 600 feet to the south
With that sidewalk, the current contract gives the Jonathan Dickinson entrance a short pedestrian connection. It does not bring the separated path that far south.
Why the Path Stops at Bridge Road Until at Least FY2029
The southern continuation is a separate FDOT project, number 443505-1. It covers 1.93 miles of U.S. 1 from SE Bridge Road to the Hobe Sound Wildlife Refuge, and FDOT's notes identify it as the Martin County US-1 Shared Use Path. In FDOT's work program report dated July 17, 2026, which went into the Martin MPO's September 2026 technical committee packet, the project totals $11,212,515. Its construction dollars, $6,905,596 and $1,443,965 from two funding sources, sit in the 2029 column.
FDOT's work program runs on a fiscal year from July 1 to June 30. That puts construction money for the refuge segment in the window from July 2028 through June 2029. The northern path's anticipated completion is Summer 2028. So the likely order is a finished path from Osprey Street to Bridge Road first, followed by a funding window for the southern link that opens about when the northern work wraps up.
| Segment of U.S. 1 | Length | What it adds | Timing per FDOT |
|---|---|---|---|
| Osprey Street to SE Heritage Blvd, contract E4X97 | 1.02 miles | Resurfacing only | Started May 2026, anticipated completion November 2026 |
| Bridge Road to Osprey Street, contract T4738 | 3.07 miles of path within a 5.1-mile resurfacing job | 12-foot separated path, west side | Listed as active, anticipated completion Summer 2028 |
| Bridge Road to Hobe Sound Wildlife Refuge, project 443505-1 | 1.93 miles | Shared-use path | Construction funds in FY2029 |
On paper the two Greenway pieces have always gone together. When WPTV reported the plan in January 2026, Martin County and FDOT described an extension built in two sections, Osprey Street to Bridge Road and then Bridge Road to the refuge, as a safer link between Seabranch Preserve State Park and Jonathan Dickinson State Park. The schedule now splits them. The Seabranch half gets built first, and Bridge Road is where it ends.
What Drivers on U.S. 1 Will Feel This Season
Two FDOT contracts overlap on this corridor in November. Resurfacing between Osprey Street and SE Heritage Boulevard, contract E4X97 with General Asphalt Co., Inc., started in May 2026. Its anticipated completion is this month, at a construction cost of $782,596.94. South of that, the T4738 job covers the longer stretch through Bridge Road.
FDOT says the T4738 work will be done in phases, with both daytime and nighttime work inside the project limits, and that access to businesses and residences will be maintained throughout. FDOT posts a weekly Treasure Coast traffic report on the same construction page, and that is where specific lane closures appear. The project page also lists Damelis Puentes of E Plus Engineering and Construction as the point of contact, at (786) 603-6119.
The Bridge Road and Petty Street intersections are named as drainage work sites. Anyone who uses Bridge Road to reach the farm, the beach road or Jupiter Island will likely see crews there at some point during the project.
What You Can Ride Now, and the Stops on Either Side of Bridge Road
You don't have to wait for 2028 to ride a separated path. Florida State Parks describes a 1.7-mile paved East Coast Greenway path that starts at the main parking area of Seabranch Preserve State Park, 6093 SE Dixie Highway, and runs through the park. That is the piece the new U.S. 1 path is meant to extend toward Bridge Road.
Martin County MPO planner Beth Beltran described the goal to WPTV in practical terms:
"People will have a facility that they can ride their bike on and jog on and walk on and ride their scooter on, and it will be separated from the cars."
In the same WPTV report, she said more people are choosing bikes for errands like getting "a cup of coffee or to go get dinner." In Hobe Sound, those trips start and end near Bridge Road, and the places along it fall on either side of the future trail endpoint.
North of the hinge, on the path's eventual route:
- Seabranch Preserve State Park, 6093 SE Dixie Highway. This is the existing paved Greenway segment and the northern anchor of the planned connection.
At the hinge itself:
- Hobe Sound Farms, 1425 SE Bridge Road. The farmers market runs Saturday and Sunday, 9 a.m. to 2 p.m. The farm's Country Christmas Night Market is Friday, November 13, from 6 to 10 p.m., with music, vendors and Santa.
- Hobe Sound Civic Center, 8980 SE Olympus Street. This is where FDOT held its August construction open house for the project.
South of the hinge, still waiting on the FY2029 segment:
- Hobe Sound National Wildlife Refuge visitor center, on U.S. 1 about two miles south of Bridge Road. The U.S. Fish and Wildlife Service notes that the visitor center is free and that the Refuge Beach lot on North Beach Road requires a vehicle pass.
- Jonathan Dickinson State Park, 16450 SE Federal Highway, which has both paved and off-road biking trails inside the park. Its entrance gets the new 600-foot sidewalk from Highbourne Way under the current contract.
Once the T4738 work is done, a rider leaving Seabranch can follow a separated path south to the Bridge Road intersection. The refuge visitor center is still about two miles further down U.S. 1, and per FDOT's July 2026 work program, a separated path for that stretch gets construction funding in FY2029.
Kristen and Amanda know U.S. 1 through Hobe Sound for its farm stand, its parks, and right now its construction. If you're figuring out which side of Bridge Road fits the way you get around, Kristen Danzig can walk you through the corridor street by street. Find it. Love it. Own it.